Lasselle Elementary School |
|
Building A - This building is approximately 2-1/2 weeks ahead of schedule. The slab was scheduled to be complete on 10/15/04, when in reality it was completed on 9/29/04. Lumber for this building is on site and ready to go.
Building B - This building is approximately 3-1/2 weeks ahead of schedule. The slab was scheduled to be complete on 10/22/04, when in reality it was completed on 9/29/04. Lumber for this building is on site and ready to go. Building C - This building is approximately 2-1/2 weeks ahead of schedule. The footings are scheduled to be complete by 10/15/04, half of the building is done already, and the rest very soon. Lumber for this building is on site and ready to go. Modular Buildings D, E, F, G, H, and J- The footings have been dug for Building D and F. All of Building D has been formed for the footing and half of Building F has been formed. DSA has advised that no footings are to be poured until plans are approved. Modtech has re-submitted plans after the fact of them being approved. Modtech has stopped until the plans are approved.
|
Building A slab. |
![]() Building B slab. |
|
![]() Temporary fencing at the retention pond. |
![]() Building C stage area. |