%@ Page Language="C#" ContentType="text/html" ResponseEncoding="iso-8859-1" %>
| Page 1 | Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 | Page 7 | Page 8 PCM3 Press Newsletters |
|
Sierra Vista Elementary School (5) Portables Project |
|
The General Contractor has worked steadily on this project for the last two weeks. To date, closure panels have been installed between the portables, asphalt landings have been installed at the ramps, and exterior painting has commenced. Underground electrical and low-voltage conduits have been installed; conduit risers into the buildings have also been completed. Wire pulling (power, data, and fire alarm) each began on July 31st and will conclude early next week. PCM3 anticipates that the General Contractor will complete this project on schedule, no later than August 6th. |
|
![]() This is a picture of the face of the new portables. |
![]() Shown in this pucture is a data pull box, note the extra cable in the box, this is for future breaks or extra cable needed in the building. |
![]() Shown in this picture is a asphalt ramp lo- cated at the base of the access ramp, these ramps are designed to meet ADA standards. |
![]() This is a pre-existing high voltage pull box, these pull boxes are designed to allow an easier pull of cable through the underground piping. |
| Page 1|
Page 2 | Page 3 | Page 4 | Page 5 | Page 6 | Page 7 | Page 8 PCM3 Press Newsletters |
|