Citrus Hill High School

Site work this month has really progressed. Building pads for A, B and C are all ahead of schedule by at least one month. Building A pad is scheduled to be completed on 8/27/04, it is done now. Building B pad is scheduled to be completed on 9/3/04, it is completed now. Building C pad is scheduled to be completed on 9/10/04, it is completed now. On average there is about 20 trucks importing dirt daily. So far about 52,000 cubic yards of dirt has been imported from the total of 115,000 that is needed. Both the plumbers and electricians are aware of the schedule being ahead and are on stand by for batter boards. Weekly construction meetings are taking place every Wednesday at 1:00pm. The Soils Technicians are on site every day with a soils technician testing for dirt compaction, watching for oversized rock in the dirt, and making sure the specs and plans are being followed.

compacting parking lot area
Compacting the parking lot area.
Future site Building C
Future site for Building C
west view from ballfield
Standing in the ballfield, looking east.
Fill Dirt in future classroom areas
Placing, compacting and watering fill dirt in
future classroom areas.
Trucks at the dirt export site to be loaded
Trucks lined up at dirt export site
to be loaded