This project’s Bid Opening was on June 10 th at 2pm. The following are the results thus far after some Bid Packages withdrew their Bids for various reasons such as mathematical error:

Bid Package #1

General Construction- $3,637,000.00

Bid Package #2

Plumbing- $893,000.00

Bid Package #3

HVAC- $321,000.00

Bid Package #4

Electrical- $801,100.00

Bid Package #5

Low Voltage- $439,302.00

Bid Package #6

Roofing- $196,175.00

Bid Package #7

Doors/Frames/Hardware- $158,200.00

Bid Package #8

Stucco/Lath & Plaster- $463,562.00

Bid Package #9

Glass & Glazing- $7,265.00

Bid Package #10

Drywall/Acoustic Ceiling/Insulation- $238,585.00

Bid Package #11

Painting/Wall Covering- $59,820.00

Bid Package #12

Ceramic Tile- $78,500.00

Bid Package #13

Casework- $379,390.00

Bid Package #14

Floor Covering- $137,183.00

Bid Package #15

Specialties- $68,333.00

Total Project Bid Price: $7,878,415.00

Mobilization is scheduled for July 6 th. Agreements and Notice to Proceeds have gone out to the approved Contractors. Paperwork is beginning to be received from the Awarded Contractors.

Compactor making rounds
Compactor making rounds
Picking out rocks larger than 6 inches
Picking out rocks larger than 6 inches
Skip loader smoothing out dirt dumps
Skip loader smoothing out dirt dumps
 
Page 1 | Page 2 | Page 3 | Page 4 | Page 5 | Page 6 | Page 7
PCM3 Press Newsletters