Indian Middle School

Contracts have now been awarded for 14 of 16 total prime contracts. All bids were rejected for BP #7 (Doors/Frames/Hardware) and BP #8 (Lath & Plaster). Both of these bid packages will be re-bid on 5/12/05 at 2PM.

Construction began in earnest at the IMS during April. The grading operation was in full swing during the last two weeks of April. The Building C pad was fine graded on 4/23/05. All other buildings (including portables) have been over excavated. Building A and Building B pads will be fine graded/delivered during the first week of May.

Underground plumbing rough-in began at Building C on 4/25/05. The Plumbing Contractor will be ready to roll over to Building A and Building B as soon as the grader completes each respective pad. The Electrician mobilized on 4/29/05 and will begin their Building C underground rough-in beginning 5/2/05.

On the horizon, look for footing excavation to begin at Building C and Building A during the second half of May, while all underground plumbing and electrical should also be completed during May at Building C, Building A, and Building B.

Northeast corner of property
Looking at the Northeast corner of the property
Northwest corner of property
Looking at the Northwest corner of the property

 

Northside of property
The North side of the property
Eastside of property
The East side of the property
Page 1 | Page 2 | Page 3 | Page 4 | Page 5
PCM3 Press Newsletters