Red Maple Elementary School

SITEWORK: Mow-curbs and fencing around ball fields, dumpster CMU enclosure wall, hand ball walls, and v-ditch at west of campus are complete, dugouts and some flatwork around Building B and portables have been poured, and ball fields have been finish graded. Landscaper has started with laying out and trenching for mainline and laterals in both ball fields.

BUILDING A: All color coat for stucco has been completed, roof is done accept for the standing seam metal roof, scaffold was removed, doors window frames on exterior of building are installed and painted, window glass is installed, interior walls are primed, bathrooms have been tiled and grouted, casework will start being delivered early next week.

BUILDING B: Drywall and taping are 100% complete, bathrooms are scratch coated, color coat is 100% complete for stucco on exterior, roof is 100% complete, and doors and window frames are all installed.

BUILDING C: Roof is 100%, exterior stucco color is 100% complete, drywall has been installed and taped, and plumbers, electricians, and fire protection are all 100% roughed in.

BUILDINGS D, E, F, and G: Color coat on stucco is 100% on all Buildings, casework has been installed in all classrooms, all sinks have been installed, and flatwork will begin around modulars early next week.

Casework in Building F
Casework in Building F
dugouts poured and fencing done on backstop
Dugouts poured and fencing done on backstop
Southeast side of building B
Southeast Side of Building B
West Side of Building A
West Side of Building A