| Indian Middle School plans will be on the street on 1/27/05. The first advertisement will also run 1/27/05, and the second advertisement will run 2/03/05. The pre-bid meeting will be conducted 2/09/05 at 1:00 PM beginning at the Val Verde High School site trailer. The grading bid package will bid at 2:00 PM on 2/17/05. Construction for the grading package is slated to commence on 3/7/5. Meanwhile, all remaining bid packages will bid on 3/17/05 with construction commencing on 4/04/05. The project itself shall be ready for District occupation for the school year beginning August of 2006. |
|